SAP QM Quiz 1 | Englishfreetest.com

  • Do test 20 minutes
  • Number Questions: 10 questions
  • By: englishfreetest.com

Here's the exercise 'SAP QM Quiz 1 | Englishfreetest.com' about Technical Quiz - Technical Tests.


Put your knowledge about all things technology to the test Because everything tech, from computers and the internet to software and big data, changes rapidly on a day-to-day basis, it’s now a must to stay up to date with the technology that dominates our modern day lives. Are you up to speed on what’s going on in the tech industry today? Take our quiz to find out. Test how much you know about technology

You can find more to the lesson and more exercises. Technical Quiz - Technical Tests in here.

Finally, click here to "Test" for start practice exercise .

  • Test content
    A. Acceptance charts
    B. Shewhart charts
    C. mean-value chart
    D. Statistical Graphics
    A. Controlling
    B. Quality of final product
    C. Data Quality
    D. None
    A. Multiple specifications must be stored in an inspection plan
    B. You cannot create multiple specifications using the Engineering Workbench (EWB)
    C. You can create the multiple specifications in a new inspection plan, but not on an existing inspection plan
    D. You need to define object types permitted for multiple specifications, but not objects for each object types
    A. Equipment
    B. Material
    C. Quality Record
    D. Production Planning Tools
    A. Master inspection characteristics
    B. Inspection Method
    C. Sampling Procedure
    D. None of these
    A. MRP Type
    B. Inspection Type
    C. Sample Determination
    D. Requirements for the vendor’s QM system
    A. Sample categories
    B. Number of physical samples
    C. Physical-sample sizes
    D. All of the above
    A. You can employ interfaces as required, such as an XML interface but not for transfer of question lists
    B. You can combine official documents, materials, notes, texts and personal input with the data objects used in Audit Management
    C. You can determine the relevant partners for each auditing phase and communicate with them
    D. Audit management is not applicable at normed standards
    A. Cost Centre level
    B. Plant level
    C. Company code level
    D. Sales Organization level