The rates of working of A and B are in the ratio 3 : 4.
Question 1:
The rates of working of A and B are in the ratio 3 : 4. The number of days taken by them to finish the work are in the ratio:
A.
3 : 4
B.
9 : 16
C.
4 : 3
Feedback
The No. of days taken by them = inverse ratio = 4 : 3.
D.
3 : 2
These questions are from this test. Would you like to take a practice test?
Practice Time and Work Online Test 5 | Englishfreetest.com
20 minutes
10 questions
Do test
Some questions from the same exam
A and B together can complete a work in 3 days. They start together. But, after 2 days, B left the work. If the work is completed after 2 more days, B alone could do the work in
Xavier can do a job in 40 days. He worked on it for 5 days and then Paes finished it in 21 days.
In how many days Xavier and Paes can finish the work?
A and B can complete a given work by working together in 8 days. B takes twice the number of days to complete the work compared to A.
In how many days A can finish the work by working alone?
A and B can do a piece of work in 4 days. If A can do it alone in 12 days, B will finish the work in
The rates of working of A and B are in the ratio 3 : 4. The number of days taken by them to finish the work are in the ratio:
A and B together can complete a piece of work in 8 days while B and C together can do it in 12 days. All the three together can complete the work in 6 days.
In how much time will A and C together complete the work?
A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours.
All the machines are started at 9 a.m. while machine P is closed at 11 a.m. and the remaining two machines complete the work.
Approximately at what time will the work be finished?
Ajay is twice efficient as Vijay. If Vijay can complete the work in 48 days, find the number days to complete the work if both work together.
A does 4/5 of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days.
How long B alone would take to do the whole work?
If 4 men or 6 boys can finish a work in 20 days.
How long will 6 men and 11 boys take to finish the same work?
Some other questions you may be interested in
You will benefit ..................... regular practice.
I have invited Mark and Mary. ..................... Harry, I don’t care whether he comes or not.
You are …………………. too much these days.
There was a …………………… cigarette end in the ashtray.
Having ………………… for ten hours, I felt great.
Not …………………… what to do, I went home.