If 4 men or 6 boys can finish a work in 20 days. How long will 6 men and 11 boys take to finish the same work?
A.10 days
B.6 days
Feedback4 men = 6 boys Then, 1 boy = 4/6 men = 2/3 men 11 boys = 2/3 × 11 men = 22/3 men Then, 6 men + 11 boys = 6 + 22/3 men = 40/3 men 1 work done = 4 men × 20days That is, 4 × 20 = 40/3 × ? days ? days = 4 × 20 × 3/40 = 6 days
C.7 days
D.4 days