A can do a piece of work in 40 days, B can do the same in 30 days.
Question 1:
A can do a piece of work in 40 days, B can do the same in 30 days. A started alone but left the work after 10 days, then B worked at it for 10 days. C finished the remaining work in 10 days. C alone can do the whole work in?
A.24 days
Feedback10/40 + 10/30 + 10/x = 1 x = 24 days
B.30 days
C.44 days
D.17 1/2 days