A and B can do a piece of work in 12 days and 16 days respectively.
Question 1:
A and B can do a piece of work in 12 days and 16 days respectively. Both work for 3 days and then A goes away. Find how long will B take to complete the remaining work?
A.15 days
B.12 days
C.10 days
D.9 days
Feedback3/12 + (3 + x)/16 = 1 x = 9 days